Repairs to runway in Tan Son Nhat airport completed

Repairs to the 25R/07L runway at Tan Son Nhat International Airport in HCM City were completed and it was put into operation at 17:30 on July 20, according to the Airports Corporation of Vietnam (ACV). 

The repairs were completed 12 hours earlier than planned and the runway was only closed from 10:48 to 17:30. 

The airport was forced to close the runway for repair due to damage caused by lighting in a thunderstorm in the night of July 19. 

After receiving a report from the ACV, the airport authority and the Civil Aviation Administration of Vietnam agreed to allow the airport to temporarily close the runway to serve the repairs from 10:48 on July 20 to 17:00 on July 21, causing the airport’s capacity to temporarily be reduced from 42 to 32 flights per hour. 

The incident forced airlines to adjust their plans and draw up possible scenarios. However, there has been no specific information on the number of flights delayed by the incident.
Mời quý độc giả theo dõi VOV.VN trên

Related

Tan Son Nhat Airport opens new parking
Tan Son Nhat Airport opens new parking

Tan Son Nhat International Airport has opened a 10,000sq.m parking garage, located outside the domestic terminal. 

Tan Son Nhat Airport opens new parking

Tan Son Nhat Airport opens new parking

Tan Son Nhat International Airport has opened a 10,000sq.m parking garage, located outside the domestic terminal. 

Tan Son Nhat Airport faces rising over-crowding
Tan Son Nhat Airport faces rising over-crowding

Ho Chi Minh City’s Tan Son Nhat International Airport will reach its 40 million passenger per annum capacity by 2018 a conference recently heard.

Tan Son Nhat Airport faces rising over-crowding

Tan Son Nhat Airport faces rising over-crowding

Ho Chi Minh City’s Tan Son Nhat International Airport will reach its 40 million passenger per annum capacity by 2018 a conference recently heard.