Another delay pushes deadline for second Hanoi metro to 2022

The operational deadline for Nhon-Hanoi Railway Station metro line has been pushed back a year to December 2022.

A construction worker uses a winch to fix the hook to the rail at Nhon-Hanoi Railway Station site in Hanoi in March, 2019. Photo by VnExpress/Ngoc Thanh.
Announcing the new deadline, Hanoi authorities said Friday that 99.5 percent of the elevated railway and 61 percent of the elevated stations have been built. The elevated section is scheduled to begin operations in April 2021.

But the underground section is only 5 percent done and work on it expected to be complete in 2022, they added.

The first of 10 trains for the second railway route, designed and manufactured by French contractors, will be delivered July next year instead of March as previously announced.

The total investment capital for the project remains at the VND30.2 trillion ($1.3 billion) announced by the government in 2014.

This is the second delay the Nhon-Hanoi Railway Station project has experienced. Work originally began in September 2010 and was set for completion in September 2017. But early in 2017, Hanoi authorities extended the deadline to 2021.

The route, the capital’s second metro line after Cat Linh-Ha Dong, runs 12.5 kilometers from Nhon area in the western districts of Nam Tu Liem, Bac Tu Liem, Cau Giay via Kim Ma Street to Hanoi Railway Station in the downtown area. It will run 8.5 kilometers on elevated tracks through eight stations and the remaining four kilometers underground.

Hanoi’s first metro line, connecting Cat Linh Station in downtown Dong Da District to the Yen Nghia Station in Ha Dong District, is said to be 99 percent complete, also having missed its deadline several times.

Mời quý độc giả theo dõi VOV.VN trên

Related

Hanoi to build new metro section in 2021
Hanoi to build new metro section in 2021

Hanoi plans to borrow $1.48 billion from official development assistance funds (ODA) to build a metro section in 2021.  

Hanoi to build new metro section in 2021

Hanoi to build new metro section in 2021

Hanoi plans to borrow $1.48 billion from official development assistance funds (ODA) to build a metro section in 2021.  

Commuter bus system would link to Metro Line No.1
Commuter bus system would link to Metro Line No.1

Ho Chi Minh City’s Department of Transport wants to develop a commuter bus system to link to stations on Metro Line No1, which is still under construction.

Commuter bus system would link to Metro Line No.1

Commuter bus system would link to Metro Line No.1

Ho Chi Minh City’s Department of Transport wants to develop a commuter bus system to link to stations on Metro Line No1, which is still under construction.

HCM City to submit new plan for Metro Line No1 in July
HCM City to submit new plan for Metro Line No1 in July

The council for appraisal and adjustment of the Metro line No 1 and No 2 project of Metro Line No 1 project plans to submit a newly adjusted plan for the metro projects to the City People's Committee for approval in July.

HCM City to submit new plan for Metro Line No1 in July

HCM City to submit new plan for Metro Line No1 in July

The council for appraisal and adjustment of the Metro line No 1 and No 2 project of Metro Line No 1 project plans to submit a newly adjusted plan for the metro projects to the City People's Committee for approval in July.