PM pushes to speed up Chau Doc - Can Tho - Soc Trang expressway construction

Prime Minister Pham Minh Chinh chaired a teleconference on March 18, connecting permanent Government members with ministries, agencies and localities to address bottlenecks stalling the Chau Doc - Can Tho - Soc Trang expressway project in the Mekong Delta.

Spanning 188.2km, the four-lane expressway is set to cut through Can Tho city and the provinces of An Giang, Hau Giang, and Soc Trang. With an estimated cost of VND44.69 trillion (over US$1.7 billion), the project is divided into four sub-projects, each managed by the local People’s Committees. Construction began in June 2023 and aims for basic completion in 2026 and full operation in 2027.

The expressway, running along a horizontal axis across the Mekong Delta, promises to slash travel time between An Giang and Ho Chi Minh City. Moreover, it will connect to Tran De port of Soc Trang province, a key gateway and economic driver for the region, facilitating the transit of exports and imports not just for Vietnam but also for Cambodia and the broader Mekong sub-region.

Progress varies across the project, with land clearance mostly done and construction hitting 15–46% completion in different segments. However, delays plague the Can Tho and Soc Trang sections, hampered by a shortage of sand for roadbeds, seasonal flooding, and the region’s soft soil.

In his closing remarks, PM Chinh framed the expressway as part of Vietnam’s goal to complete 1,200km of expressways this year, en route to a national target of 3,000km by the Government term’s end.

He noted that since taking office, the Government has prioritised securing investments for transport infrastructure to ease transport-related bottlenecks in the Mekong Delta, helping foster socio-economic development, ensure security - defence, create new development spaces, facilitate production, business and job creation, and guarantee social welfare in the region.

He requested local authorities to embrace their responsibilities and rally the entire political system and armed forces for better coordination and effectiveness. Contractors were urged to adopt more proactive and flexible approaches to accelerate progress to meet the June 2026 deadline.

The Government leader called for a spirited emulation movement, tighter inspections, and prompt recognition of successes, as well as strict action against delays tied to corruption or misconduct. Issues beyond the power of local authorities must be forwarded to the Government for consideration.

Mời quý độc giả theo dõi VOV.VN trên
Viết bình luận

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

Related

PM inspects Can Tho-Ca Mau Expressway project
PM inspects Can Tho-Ca Mau Expressway project

Prime Minister Pham Minh Chinh on December 15 inspected the construction of the Can Tho–Ca Mau Expressway, during which he encouraged workers at the site and directed measures to speed up the project's progress.

PM inspects Can Tho-Ca Mau Expressway project

PM inspects Can Tho-Ca Mau Expressway project

Prime Minister Pham Minh Chinh on December 15 inspected the construction of the Can Tho–Ca Mau Expressway, during which he encouraged workers at the site and directed measures to speed up the project's progress.