HCM City approves 30-storey administrative centre project
VOV.VN - Ho Chi Minh City has approved a major project to develop a new administrative centre and central square in the Thu Thiem New Urban Area, with the 30-storey administrative building forming the centrepiece of a complex estimated to cost around US$1.1 billion.
Under a decision, the municipal People’s Committee approved the project under the public-private partnership (PPP) model, using a build-transfer (BT) contract.
Located in An Khanh ward in the Thu Thiem New Urban Area, the project covers approximately 46.72ha and comprises four components: technical infrastructure and supporting facilities, including underground parking in the landscaped park area; the city administrative centre; a conference and performance centre; and the city’s central square.
30-storey centre to consolidate administrative offices
The administrative centre will comprise 30 above-ground floors, two basement levels and a technical rooftop structure, with a total construction floor area of approximately 389,100 square metres.
The building will occupy a site of around 78,363 square metres and is designed to accommodate the city’s administrative offices in a modern, centralised complex.
The project aims to improve the efficiency of state administration, streamline the organisation of government agencies and reduce the fragmentation of administrative offices. It is also intended to improve the quality of public administrative services and create more convenient access for residents and businesses.
The wider development will include landscaped areas and public spaces, contributing to the architectural and urban landscape of the Thu Thiem area.
VND29.6 trillion investment under PPP model
The entire project has an estimated investment of VND29.616 trillion (US$1.1 billion). Its other components include technical infrastructure, supporting facilities and underground parking, as well as a conference and performance centre with an expected capacity of around 2,000 seats.
The central square, covering approximately 119,000 square metres, is expected to accommodate around 268,000 people for political and major public events and up to 500,000 for cultural festivals.
The investor is Saigon Sun Investment and Development Company Limited, part of Sun Group. The project is being implemented under a BT contract, with payments expected to combine land funds and the city budget in accordance with regulations.
Construction is scheduled to take place from 2026 to 2028, including work undertaken by the investor before the BT contract is signed.