(VOV) - The inauguration ceremony of two trillion-dong tunnels at Thanh Xuan and Trung Hoa interchanges was held in Hanoi on January 8.
![]() |
One tunnel is at Thanh Xuan interchange (at the junction of Nguyen Trai-Khuat Duy Tien roads) and the other is at Trung Hoa interchange (at the junction of Tran Duy Hung road and Thang Long boulevard). |
![]() |
The two tunnels totally cost VND1,638 billion. It is a component in the second phase of Hanoi’s third ring road linking Mai Dich to North Linh Dam. |
![]() |
After inauguration, the two tunnels are expected to help ease traffic congestion at interchanges. |
![]() |
The 700m-long tunnel at Trung Hoa interchange in Cau Giay District has three lanes for motor vehicles. It costs VND1,087 billion. |
![]() |
![]() |
The tunnel is completed after 11 months of construction, and 7 months ahead of schedule. |
![]() |
Trung Hoa interchange will facilitate transportation from urban area to Thang Long boulevard and vice versa. |
![]() |
![]() |
![]() |
Floral decoration. |
![]() |
Construction of the 980m-long tunnel at Thanh Xuan interchange began on June 2014. It has an investment capital of VND551 billion sourced from Japan’s ODA. |
![]() |
Each tunnel has two lanes for motor vehicles with a designed speed of 60km/h. |
![]() |
![]() |