PM orders fast-track construction of Lao Cai - Hanoi - Hai Phong railway

Prime Minister Pham Minh Chinh has signed an official dispatch requesting expedited construction of Lao Cai – Hanoi – Hai Phong railway.

The official dispatch was sent to the Ministers of Construction, Foreign Affairs, Agriculture and Environment, and Finance, Secretaries of the provincial/municipal Party Committee and Chairpersons of the provincial/municipal People’s Committees of Hanoi, Lao Cai, Yen Bai, Phu Tho, Vinh Phuc, Bac Ninh, Hung Yen, Hai Duong, and Hai Phong.

The Minister of Construction was asked to work closely with local authorities to hasten land clearance, compensation, resettlement, site surveys, and the drafting of a feasibility study, which must be completed by June 2025, setting the stage for the project's groundbreaking on December 19, 2025.

To meet this timeline, the minister must direct project management boards and consulting units to mobilise additional personnel. Teams will work around the clock, including holidays and weekends, to simultaneously prepare, appraise, and approve the feasibility study, detailed construction designs, bidding documents, and other essential procedures.

The minister was required to promptly finalise the National Assembly's draft resolution on special mechanisms and policies to support railway development. The draft must be submitted to the legislature’s upcoming 9th meeting for review and reported to the Government by May 5.

The Chairpersons of the above provincial/municipal People’s Committees must urgently establish local steering committees for land clearance by May 5. These committees, led by the respective Secretaries of the provincial/municipal Party Committees, will oversee the completion of compensation, resettlement, and the feasibility study by August 2025.

Other specific tasks were assigned to relevant ministers and localities to support the project’s progress. Deputy Prime Minister Tran Hong Ha will directly oversee the project and address any arising obstacles.

pm chinh_0.jpg

PM calls for bold, accelerated action in railway development

Prime Minister Pham Minh Chinh urged ministries, agencies, and localities to act with “greater speed and boldness” to carry out Vietnam’s railway projects at the second meeting of the Steering Committee for key national railway projects in Hanoi on April 26.

Mời quý độc giả theo dõi VOV.VN trên
Viết bình luận

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

Related

Gov't demands starting work on North – South high-speed railway by end of 2026
Gov't demands starting work on North – South high-speed railway by end of 2026

The Government on April 23 issued Resolution No. 106/NQ-CP that details the roadmap for implementing the North – South high-speed railway project, requesting all necessary conditions be completed to commence construction no later than December 31, 2026.

Gov't demands starting work on North – South high-speed railway by end of 2026

Gov't demands starting work on North – South high-speed railway by end of 2026

The Government on April 23 issued Resolution No. 106/NQ-CP that details the roadmap for implementing the North – South high-speed railway project, requesting all necessary conditions be completed to commence construction no later than December 31, 2026.