The operator of Japan's crippled nuclear plant laid out a blueprint on Sunday for stopping radiation leaks and stabilizing damaged reactors within the next six to nine months as a first step toward allowing some of the tens of thousands of evacuees to return to the area.

On orders from Prime Minister Naoto Kan, TEPCO drew up the blueprint and publicly explained its long-term strategy — for the first time since the disaster — for containing the crisis that has cast a cloud of fear over the country.

Under the roadmap, TEPCO will deal with the crisis in two stages. In the first stage, the company will focus on cooling the reactors and spent fuel pools and reducing the level of leaking radiation. It will also aim to decontaminate water that has become radioactive, reduce the amount of radiation released into the atmosphere and soil, and lower radiation levels in the evacuation area, Katsumata said.

In the next stage, TEPCO aims to firmly control the release of radioactive materials, achieve a cold shutdown of the reactors and temporarily cover the reactor buildings, possibly with a form of industrial cloth. Longer-term goals include removing fuel from the spent fuel pools and putting permanent covers over the buildings.

TEPCO also plans to establish a system to recycle cooling water that will remove radioactivity as well as corrosive salt left behind by seawater that was earlier used as an emergency cooling measure.

AP